Every Frankhaus kitchen passes through the same five stages. The duration and outcome of each are defined in advance, so that the entire process is predictable from the outset.

  1. Discovery 1 week
  2. Survey 1 day
  3. Design 2–3 weeks
  4. Production 5–6 weeks
  5. Installation 3–5 days
Typical duration
10–12 weeks
Installation
Our own team
The Experience Centre, with graphite and concrete kitchens on a polished concrete floor

Five stages,
one team.

Skip this section
  1. Step 1: Discovery

    The first meeting takes place at the Experience Centre or at your home. Cooking routines, storage requirements and the movement of daylight through the room are discussed, and the meeting concludes with a written brief and an initial layout proposal.

    Duration
    1 week
    Outcome
    Written brief, first layout
    A kitchen elevation on a drafting table with a steel rule and pencil
  2. Step 2: Survey

    Our team surveys the room on site, recording the walls, corners and every service point. The final survey is taken once screed and plaster are complete, and forms the basis for production.

    Duration
    1 day
    Outcome
    Survey report
    An open-plan kitchen with concrete walls and a lake view
  3. Step 3: Design

    Layout, surfaces and appliances are finalised together. Once the drawings and itemised quotation are complete, the design is formally approved, and from that point the price and delivery date are fixed.

    Duration
    2–3 weeks
    Outcome
    Approved design and quotation
    An anthracite kitchen wall divided by lines of light
  4. Step 4: Production

    Every part is made on our own production line in Istanbul. Units are pre-assembled and inspected before leaving the workshop, and progress is reported to you every week.

    Duration
    5–6 weeks
    Outcome
    Inspected units
    A CNC router at work in a workshop lit with cold light at night
  5. Step 5: Installation

    Our own installers protect floors and surrounding surfaces, fit the units and set the worktop and appliances. Every door is adjusted and every mechanism tested. A second visit for final adjustment follows a few weeks after handover.

    Duration
    3–5 days
    Outcome
    Handover, care guide
    A finished kitchen with a basalt island facing a misty pine forest

The project
timeline.

The timeline below illustrates a typical project. Collection and appliance lead times may alter it by a few weeks; the exact schedule is confirmed in writing at design approval.

  1. Discovery Week 1
  2. Survey Week 2
  3. Design Weeks 3–5
  4. Production Weeks 6–11
  5. Appliance supply Alongside production
  6. Installation Week 12
  7. Milestones Design approval · Week 5 — Handover · Week 12

Handover and
final adjustment.

A few weeks after handover, a second visit is made to carry out the final adjustments. For all subsequent support, we may be reached by e-mail.

A finished kitchen with a white lacquer island and smoked-glass cabinets, looking out over a misty bay

Preparing for the
first meeting.

Existing plans, photographs and notes make the first meeting more productive. Providing them is optional; any missing information can be completed together during the meeting.

Request a visit
  1. Plan or sketch

    An architectural plan in DWG or PDF format or, failing that, a hand-drawn sketch. Approximate dimensions suffice; the exact survey is taken by our team.

  2. Photos of the room

    Every wall, the windows, columns and beams, and the water, gas and electrical points.

  3. Appliance list

    The models of the built-in appliances you have in mind. If no decision has been made yet, the selection is made together.

  4. Daily use

    The number of people who cook, how often you entertain, and your breakfast and coffee routines.

  5. Storage requirements

    Pantry, small appliances, cookware and tableware: what is to remain on display and what is to be concealed.

  6. References

    Images of rooms and materials you admire. Examples you do not favour are equally instructive.

  7. Timing and budget

    Your move-in or renovation date and the intended budget range, which together frame the planning.

  8. Building works

    The status of screed, plaster and services. The final survey is taken once these are complete.

Frequently asked questions.

For any question not addressed here, please contact us by e-mail or telephone.

info@frankhaus.com.tr
+90 532 466 02 67

From first meeting to handover typically takes 10–12 weeks, of which 5–6 weeks are devoted to production. The chosen collection and appliance lead times may alter this by a few weeks. The delivery date is confirmed in writing at design approval.

No. The exact survey is taken by our team once screed and plaster are complete. A plan or approximate dimensions brought to the first meeting will, however, accelerate the layout work.

No. Appliances may be selected with us or sourced independently. The only condition is that models are confirmed before design approval, since every housing is made for the appliance itself.

Carcasses carry a 10-year warranty. Hardware and built-in appliances are supplied with their manufacturers’ own warranty terms. After handover, all requests may be addressed to support@frankhaus.com.tr.

Installation is carried out by our own team over 3–5 working days, depending on the size of the kitchen. Floors and surrounding surfaces are protected throughout, and the room is left clean on completion. Water and electrical services must be ready before installation day.

At handover, a written care guide is provided for every surface in the kitchen. Fronts should be wiped with a soft, damp cloth and stone worktops with a mild cleaner. Abrasive products and scouring pads should be avoided.

As every kitchen is made to its own dimensions, no price list is published. Following the survey and initial design, an itemised quotation is prepared. Sharing your budget range at the first meeting allows the options to be shaped accordingly.

Until design approval, the drawings are revised as often as required. After approval, changes such as colour or door style remain possible until cutting begins, and any effect on time and cost is confirmed in writing. Changes after cutting require new parts to be made.